MAJOR PROJECTS - CONTINUED
OOOYAS ISLAND
 
   
RACE DAY HOTEL, YAS ISLAND
ABU DHABI , UAE

Download the Race Day Hotel Data Sheet
 
   
   
 

Client
ALDAR PROPERTIES PJSC

Consultant
WATERMAN EMIRATES / KELLOGG BROWN & ROOT SERVICES

Main Contractor
NSCC

Contract Value
AED 14,000,000

Start Date
13/11/2007

Completion Date
3/02/2008

Project Details

Number of Piles : 877 nos
Reinforcement Steel : 581 tons
Concrete Volume : 7,087 m3
Total Length Drilled : 18,457 LM

 



 
   
 

MARRIOTT HOTEL, YAS ISLAND
ABU DHABI, UAE


Download the Marriott Hotel Data Sheet

 


Client
ALDAR PROPERTIES PJSC

Consultant
WSP MIDDLE EAST /
KELLOGG BROWN & ROOT SERVICES

Main Contractor
NSCC

Contract Value
AED 10,000,000

Start Date
01/12/2007

Completion Date
28/03/2008


Project Details

Number of Piles : 515 nos
Reinforcement Steel : 556 tons
Concrete Volume : 7,803 m3
Total Length Drilled : 10,243 m

 

 
THE GRANDSTAND, PROJECT K RACE TRACK, YAS ISLAND
ABU DHABI , UAE

Download the Grandstand Data Sheet
 
 
Client
ALDAR PROPERTIES

Consultant
TILKE

Main Contractor
CEBARCO - WTC

Contract Value
AED 15,739,549.00

Start Date
07/05/2008

Completion Date
12/08/2008

Project Details

Number of Piles : 835 nos
Reinforcement Steel : 710 tons
Concrete Volume : 11,450 m3
Total Length Drilled : 13,300 LM




 
  MARINA HOTEL, YAS ISLAND
ABU DHABI, UAE


Download the Marina Hotel Data Sheet
 
 

Client
ALDAR PROPERTIES

Consultant
DEWAN ARCHITECT & ENGINEERING

Main Contractor
KELLOG BROWN ROOT & SERVICES

Contract Value
AED 12,140,000

Start Date
02/03/2008

Completion Date
24/04/2008


Project Details
Number of Piles : 523 nos
Reinforcement Steel : 463 tons
Concrete Volume : 6292 m3
Total Length Drilled : 9155 LM
 
   
   
BACK
Home | History | Vision | Our Team | Activities | Value Engineering | Plant | Clients | Contacts